A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why short-horizon pull planning can limit visibility, weaken alignment, and prevent teams from gaining the full benefits of Takt and pull planning. Jason breaks down why pull planning should happen at the phase level, where teams can optimize the full sequence, establish zones, create buffers, anticipate procurement needs, and start pre-construction coordination months before the work reaches the field.
What you'll learn in this episode:
- Why a three-week planning horizon may not give teams enough time to anticipate future needs.
- How phase-level pull planning creates better visibility into the entire sequence of work.
- Why Takt, zones, buffers, and Little's Law become more useful when planning the full phase.
- How longer-range planning improves procurement and pre-construction coordination.
- Why planning systems should connect vertically to milestones, schedules, supply chain, and field execution.
Are you planning the entire phase far enough ahead or simply coordinating the next few weeks and calling it Lean?
If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊).
Also, here are links to our YouTube Channels:
· Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg
· LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt
· LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured
· LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Weitere Episoden von „Elevate Construction“



Verpasse keine Episode von “Elevate Construction” und abonniere ihn in der kostenlosen GetPodcast App.